| This Guide is intended to aid in the proper
design, specification, and installation of brick paving systems.
The designs presented in this Guide are not intended as a
replacement to the advice of an experienced pavement designer.
Although the proposed pavement sections may be appropriate
in developing preliminary sections and budget costs, it is
recommended that an engineer with appropriate pavement experience
certify the final design.
Click on images for larger view.
General
[top]
Flexible brick pavements, as defined in this
Guide, consist of sand set or bituminous set brick pavers
over layers of conventional pavement materials. The flexible
brick pavement shown in Figure 1 consists of a compacted subgrade
beneath a subbase layer, base layer, and setting bed surfaced
with brick pavers and jointing sand. A subbase may not always
be necessary between the subgrade and the base. An edge restraint
is provided around the flexible brick pavement as part of
the system. Sand set brick pavers, and to a lesser extent
bituminous set brick pavers, with sand filled joints, develop
interlock between adjacent pavers, which distributes the applied
loads into the underlying layers. This does not occur with
mortar set pavers. Mortared brick paving is only used over
a concrete slab and is not covered in this Guide. Although
this pavement type has been used successfully, the emphasis
in this Guide is on flexible wearing surfaces. Information
on other types of brick pavements can be found in BIAA Technical
Notes on BrickConstruction 14 Series.
Interlock is a phenomenon that occurs in segmental
pavements as a result of the interaction of the pavers and
the jointing sand between the pavers. The tight, sand-filled
joints transfer loads between adjacent brick pavers through
friction. Interlock increases over time as the joint sand
becomes thoroughly compacted and debris builds up in the joints.
When interlock is present, the wearing surface contributes
to the strength of the system. Specially-shaped pavers provide
little additional contribution to vertical interlock. However,
some bond patterns, such as herringbone, help to distribute
horizontal loads. In areas subjected to heavy vehicular traffic,
the brick pavers may be required to have a minimum thickness
to achieve sufficient interlock.
 |
Figure 1. Flexible
Brick Pavement |
Adequate design and construction results in three
types of interlock: vertical interlock, rotational interlock,
and horizontal interlock. See Figure 2. If a vertical load
were applied to a single brick in a pavement without vertical
interlock, that brick would be forced down between adjacent
bricks, transmitting concentrated stresses onto the setting
bed. Brick pavers that are compacted into the setting bed
and have well consolidated sand in the joints between them
provide shear resistance in the wearing surface. Thus, the
load is spread over a wide area of setting bed. See Figure
2. Sand set pavers develop greater vertical interlock than
bituminous set pavers as they are vibrated to compact the
sand bed and densify the joint sand to a higher degree.
|
Figure 2. Vertical
Interlock |
If a load is applied asymmetrically to an individual
brick, the brick may rotate, displacing the setting bed and
adjacent bricks. Rotational interlock holds the brick in place
while rigid edge restraints prevent the bricks from moving
laterally, thereby eliminating rotation. See Figure 3.
|
Figure 3. Rotational
Interlock |
|
Figure 4. Horizontal
Interlock |
Horizontal interlock is not achieved if horizontal
movement is allowed. In vehicular traffic areas, horizontal
braking, cornering and accelerating forces try to move pavers
along the road; this is known as creep. Sand filled joints
and an interlocking bond pattern transfer these forces within
a paving area to rigid edging. See Figure 4. Loads created
by turning vehicular traffic are distributed more evenly in
all directions by a herringbone pattern than by running bond
pattern, which has acceptable horizontal interlock in only
one direction. See Figure 5. Basket weave patterns may have
continuous joints in two directions, resulting in unacceptable
horizontal interlock. Sand set brick pavers initially develop
greater horizontal interlock than bituminous set brick pavers
as the joint sand is better compacted.
|
Figure 5. Horizontal
Load Interlock |
Although a flexible brick pavement provides a
durable surface for light or heavy vehicular applications,
the surface of a segmental pavement may not provide a smooth
ride at high speeds. Brick roads tend to slow traffic as subtle
variations in the surface cause decreasing ride comfort as
speed increases. These variations help reduce speeds in areas
where faster vehicular traffic may be a concern. This is one
of many traffic calming measures that cities use to slow traffic
in residential neighborhoods. However, segmental pavements
are not recommended where vehicle speeds exceed 40 mph (64
kph).
Deciding on the appropriate brick paving system
to use is important to ensure proper performance. Since brick
can be used in a variety of ways, as shown in Figure
6, Table 1 is provided to assist in selecting the most
appropriate system.
|
Figure 6. Brick
Paving Systems |
Part
1: Structural Design and Detailing [top]
Introduction The
AASHTO methodology was described in detail in the first edition
of this Guide. Direction was given on determining the amount
of traffic that would use the pavement, dependent on the many
factors identified in the 1993 AASHTO Design Guide. Tables
were provided for calculating the estimated traffic in the
design lane based upon axle loads, equivalency factors, structural
numbers, growth factors and lane distribution factors. The
equations used to calculate the required structural number
for the pavement, and to proportion the individual pavement
layers were set out, along with figures and tables to assess
the layer and drainage coefficients necessary to design the
pavement. In addition, nomographs and design examples were
provided to clarify the procedure.
This version of the Guide provides a method based
upon specific applications and site conditions rather than
the more complex procedure of the first edition. The design
solutions were prepared in accordance with the AASHTO methodology,
and the input values are declared in the relevant sections.
Although the proposed pavement sections may be appropriate
in developing preliminary sections and budget costs, it is
recommended that the final design be certified by an engineer
with pavement design experience.
In addition to these revisions related to the
AASHTO design method, this edition also discusses an alternative
design method for use in those states that have adopted the
Caltrans design method or derivations thereof. Design solutions
are not provided using this method, but gravel equivalent
factors are suggested for use with the Caltrans manual, so
that it can be adapted to consider brick pavers.
Because of the range of climates and the variability
of soils, base and subbase materials, designers must use good
engineering judgment in detailing a flexible brick paving
system. The designer should be acquainted with site conditions
and use all available resources to create a cost-effective
solution. Consult references listed at the end of this Guide
for more information.
Table 1 Brick Paving System Selection
[top]
| System |
Advantages |
Disadvantages |
Flexible brick paving
over flexible base (Fig. 6a) |
Most durable over time
Easy to repair utilities
Usually most economical
Allows use of semi-skilled labor
|
May require a thicker base
Permits some water percolation through system
|
Flexible brick paving over semi-rigid
base
(Fig. 6b) |
Good as an overlay to existing pavement
Good over poor soils or small, confined areas
Better aesthetic repairs than continuous concrete |
Requires good drainage
More expensive
Vulnerable to frost heave |
| Setting sand system |
Good load transfer
Simple and expedient installation
Pavers easily reused for repairs |
Susceptible to deficiencies in the bedding sand
Susceptible to sand loss and creep issues |
| Bituminous setting system |
Enhanced water resistance
Good containment of setting bed material
Less onerous edge restraint requirements |
More expensive and slower to install
Pavers difficult to salvage during repair work
Poor tolerance to paver thickness variations or poor
base elevations |
Mortared paving over rigid base
(Fig. 6d) |
Matches adjacent walls with mortar joints
Good over poor soils
Can be used on steeper grades |
Must have a concrete base
Most costly of all brick paving
Requires maintenance of mortar joints
Requires movement joints |
Subgrade
Classification [top]
The subgrade is classified by the existing soil
conditions, the environment and drainage. The more accurate
the subgrade classification, the better the performance of
the pavement.
Table 2 Subgrade Categories [top]
| Subgrade Category |
CBR Range |
R-value Range |
| Unsuitable |
< 2.9 |
< 6 |
| Poor |
3.0 - 5.9 |
6 - 13 |
| Fair |
6.0 - 9.9 |
14 - 24 |
| Good |
10.0 - 14.9 |
25 - 38 |
| Excellent |
> 15.0 |
>38 |
Table 3 Subgrade Categories from USCS
USCS
Designation |
Environmental/Drainage
Conditions |
| Wet |
Average |
Dry |
Frost |
| GW |
E |
E |
E |
E |
| GP |
E |
E |
E |
E |
| GW-GM |
E |
E |
E |
G |
| GW-GC |
E |
E |
E |
G |
| GP-GM |
E |
E |
E |
G |
| GP-GC |
E |
E |
E |
G |
| GM |
E |
E |
E |
P |
| GC` |
E |
E |
E |
P |
| GM-GC |
E |
E |
E |
P |
| SW |
E |
E |
E |
E |
| SP |
G |
E |
E |
E |
| SW-SM |
G |
E |
E |
F |
| SW-SC |
G |
E |
E |
F |
| SP-SM |
G |
E |
E |
F |
| SP-SC |
F |
G |
E |
F |
| SM |
G |
E |
E |
U |
| SC |
F |
G |
E |
P |
| SC-SM |
G |
E |
E |
U |
| CL |
P |
F |
G |
P |
| CL-ML |
P |
F |
G |
U |
| ML |
P |
F |
G |
U |
| OL |
U |
U |
U |
U |
| CH |
P |
P |
F |
P |
| MH |
P |
F |
F |
U |
| OH |
U |
U |
U |
U |
Soil Conditions
The
existing soil conditions for a project should be determined
prior to commencing the design of the pavement sections. A
geotechnical engineer who specializes in site investigation
work will generally test and classify the soil conditions
for the project area. Testing will be carried out at the project
site and samples will be recovered for additional testing
in the laboratory.
The site investigation should include test pits
and borings along the alignment of the road or street, or
over the area of the pavement. Samples should be collected
for the following laboratory tests considered essential to
determine the engineering properties of the soils over which
the pavement will be constructed:
- Grain-size distribution: sieve analysis test
and hydrometer test to determine the percentage of the individual
grain sizes in the sample;
- Atterberg Limits: consistency tests to determine
the moisture content at which the sample changes from a
semi-solid state to a plastic state (Plastic Limit) and
from a plastic state to a liquid state (Liquid Limit);
- Natural moisture content: test to determine
the in-place moisture content of the soil;
- Natural Density: test to determine the in-place
density of the soil;
- Dry density/optimum moisture content relationship
(standard or modified): compaction test to determine the
ideal moisture content to achieve the specified state of
compaction;
- Strength tests [California Bearing Ratio (CBR)
or Resistance Value (R-value)]: mechanical tests to determine
the bearing capacity of the soil for use in the design.
The CBR test method is set out in ASTM D 1883
Test Method for CBR of Laboratory Compacted Soils (AASHTO
T193). It can be conducted on treated and untreated base,
subbase and subgrade materials. This test is a comparative
measure of the load-bearing capacity of a soil. It measures
the load required to drive a standard plunger a set depth
into a sample of soil at a standard rate of penetration. The
CBR value is the ratio of the load measured in the test and
the load used to achieve the same penetration in a standard
sample of crushed stone. The test is generally undertaken
in the laboratory, but in-place tests can also be carried
out. The values are greatly affected by the degree of compaction
and the moisture content of the specimen. The test should
be conducted on a specimen compacted to a density representative
of the material to be used in the pavement, or alternatively
at a range of densities likely to be encountered. To represent
the materialŐs potential moisture condition in the pavement,
the test should be conducted on specimens that have been soaked
after compaction for a period of four days.
The R-value test method is set out in ASTM D
2844 Test Method for Resistance R-Value and Expansion Pressure
of Compacted Soils (AASHTO T190). It can be conducted on treated
and untreated base, subbase and subgrade materials, but the
test can only be undertaken in the laboratory. For base, subbase
and non-expansive granular soils, the R-value is determined
at a density equivalent to the density used during construction.
For cohesive soils and expansive granular materials, the R-value
test involves two separate procedures. One procedure calculates
the estimated thickness of the overlying pavement layers required
to maintain the state of compaction of the material. The other
procedure estimates the thickness of the overlying pavement
layers required to prevent plastic deformation in the material.
The R-value is determined at the moisture content and density
at which the thickness of overlying materials is similar in
the two procedures.
The AASHTO design method uses the resilient modulus
(MR) as the design input for the subgrade properties. The
mean value of all test results for each pavement section or
soil type should be used for design. The test to directly
determine MR is not widely used, so AASHTO has proposed the
following relationships between the CBR and R-value test results.
These relationships are as follows:
MR (MPa) = 10.3 X CBR (Eq.
1)
Where: MR is the resilient modulus and CBR is the California
Bearing Ratio
MR (MPa) = 6.9 + 3.8 X R-value (Eq.
2)
The Caltrans design method uses the R-value as
the design input for the subgrade properties. The lowest R-value
should be used for design over a section of pavement. However,
if there are one or two significantly lower R-values in a
localized section, consideration should be given to replacing
these areas with better material and using the next lowest
value.
Soils or subgrades are typically classified into
different groups to represent their engineering properties.
There are several systems used in the United States, but the
two most common are the Unified Soil Classification System
(USCS), used for general engineering purposes, and the AASHTO
System, used for highway engineering purposes. The USCS is
set out in ASTM D 2487 and the AASHTO system is set out in
AASHTO Standard M145, Classification of Soils and Soil-Aggregate
Mixtures for Highway Construction.
In the USCS, the soils are classified in twenty-five
groups by two letter designations dependent on the soil type
and physical properties. The first letter represents the main
soil type (gravel, sand, silt, clay or organic), and the second
modifies the first letter based upon the grain-size distribution
for granular soils or the Atterberg Limits for cohesive soils.
Eleven groups have paired designations. In the AASHTO system,
the soils are classified in seven main groups (and in twelve
sub-groups) based upon their grain-size distribution and Atterberg
Limits. The two systems are given in Tables 3 and 4, in a
manner that correlates each group with the suggested subgrade
categories (U -unsatisfactory, P - poor, F - fair, G - good,
E - excellent).
A geotechnical engineer’s report will include
a description of the soils encountered at the project site
and will set out the test results. In addition, it will generally
provide recommendations on the strength properties of the
soils to be used for design and may contain some design options
for the pavement section. If a recommended value is given
in the report, this should be used to select the subgrade
category (see Table 2). If there is no recommended value,
but CBR or R-value test results are given, the average of
these values should be used for the AASHTO design methodology.
When the design is to be undertaken using the Caltrans adaptation,
the minimum R-value should be used for selecting the subgrade
category. If only the subgrade’s USCS or AASHTO classification
is known, Table 3 or 4 can be used to estimate the subgrade
category from the column titled “Average”. The
remaining columns are addressed in the following section.
Environment and
Drainage [top]
Environmental conditions and the quality of subgrade
drainage can have a major effect on the support offered by
the subgrade. In wet climates, poorly drained areas, or those
that experience freezing conditions, the subgrade support
is likely to be reduced during certain periods of the pavement's
life. Conversely, in arid climates or well-drained areas,
it is likely that a higher degree of subgrade support will
be experienced during part of the pavement's life. These factors
can have a significant effect on the performance of the pavement.
Saturation of the subgrade, and the materials
in the pavement section, can lead to premature distress as
this condition reduces the strength of these materials. Water
can enter the pavement through the joints between bricks,
through cracks and joints in the bound base materials, or
from a high ground water condition. The amount of water penetrating
from the surface depends on the regional climate. Fluctuations
in moisture content can also be problematic, leading to changes
in volume and load support. Rapid removal of water from the
pavement is therefore an important design objective, and a
positive drainage system should be considered. Design of such
a system is beyond the scope of this Guide.
Table 4: Subgrade Categories from AASHTO
AASHTO
Designation |
Environmental/Drainage
Conditions |
| Wet |
Average |
Dry |
Frost |
| A-1-a |
E |
E |
E |
E |
| A-1-b |
E |
E |
E |
E |
| A-2-4 |
E |
E |
E |
G |
| A-2-5 |
E |
E |
E |
G |
| A-2-6 |
E |
E |
E |
G |
| A-2-7 |
E |
E |
E |
G |
| A-3 |
E |
E |
E |
P |
| A-4 |
E |
E |
E |
P |
| A-5 |
E |
E |
E |
P |
| A-6 |
E |
E |
E |
E |
| A-7-5 |
G |
E |
E |
E |
| A-7-6 |
G |
E |
E |
F |
Figure 7 presents the six climatic regions experienced
in the United States. It depicts two regions of hard freezes
where spring thaw conditions are likely to affect the subgrade,
two regions where there is a potential effect from frost,
but only if the pavement is thin, and two regions not susceptible
to frost. Average depths of frost penetration are indicated
for the eastern and central states, although frost depths
can vary locally based on many factors. Local data should
be used in its place if this is available for a specific project
site. This is particularly true in the western states, and
no frost depth data is therefore included in Figure 7 for
this part of the country. If the depth of frost penetration
is greater than the pavement thickness determined in this
Guide based on one of the first three columns of Tables 3
and 4, it will be necessary to revise the pavement construction.
Either non-frost susceptible material should be added to the
thickness of the pavement section so that it is thicker than
the depth of penetration, or a revised depth should be determined
based upon the anticipated loss of strength in the subgrade.
In this case, if the project is located in Regions III or
VI on Figure 7, it will be necessary to use the subgrade category
from the column for Frost Environmental/ Drainage Conditions.
If the project is located in Regions II or V, and the project
site drains poorly, it will also be necessary to use the Frost
Environmental/ Drainage Conditions column to determine the
subgrade category, since, once again, pavement thickness is
a factor.
The AASHTO design method utilizes an effective
resilient modulus that is derived from the seasonal resilient
moduli. These vary depending on the moisture conditions of
the subgrade during each season. Such an analysis is beyond
the scope of this Guide. It is recommended that the design
be undertaken using a subgrade category as described earlier
or from the geotechnical report, as the geotechnical consultants
will consider these factors when providing their recommendations.
If these values are not available, but the USCS or AASHTO
designation is known, Tables 3 and 4 should be used to develop
the appropriate subgrade category. Most pavements should be
designed using the subgrade category from the column for Average
Environmental/Drainage Conditions. However, if the project
is located in Regions I, II or III of Figure 7, and the project
site drains poorly, such that the subgrade is frequently saturated,
it will be necessary to use the subgrade category from the
column for Wet Environmental/Drainage Conditions. If the project
is located in Regions IV, V or VI and the project site drains
well, such that the subgrade is rarely saturated, it may be
appropriate to use the column for Dry Environmental/ Drainage
Conditions.
Traffic
Analysis [top]
The traffic analysis for the project should be
undertaken before commencing design of the pavement sections.
A traffic engineer is typically contracted for this work.
When undertaking a design it is necessary to determine the
existing (or initial) traffic volume using the road, and to
estimate the future traffic volumes over the analysis period.
Based upon these data and local experience, it is necessary
to establish the traffic flow in each direction and in the
design lane. Most of the damage to a pavement is caused by
truck traffic; passenger cars, pick-ups and light two axle
trucks generally have a negligible effect. Using local data
on the anticipated types of vehicles that will use the road,
the number of load applications of each axle group can be
calculated. Next, all of the repetitions of each axle group
are converted into the equivalent number of repetitions of
one axle load condition.

In the AASHTO design methodology, the traffic
is represented as the equivalent number of load applications
of an 18-kip axle load that represents the mixed traffic using
the pavement. This is known as an equivalent single axle load
(ESAL). Tables in the AASHTO Design Guide provide values for
converting different axle loads into ESALs.
In the Caltrans method, this number of ESALs
is further converted into a traffic index (TI). This varies
in accordance with Equation 3 below, except that the TI is
rounded to the nearest 0.5:
TI = 9.0 X (ESAL/106)0.119 (Eq.
3)
In this Guide, a simplified approach is adopted
using pavement classes. Nine pavement classes are identified
in Table 5, together with a description of their anticipated
use and an indication of the total number of ESALs and TI
for each class.
The life of the pavement can be expressed in
a number of ways depending on local policy. Two terms are
used in the AASHTO Design Guide covering different long-term
strategies. These are the performance period and the analysis
period. The performance period is the length of time that
a pavement will remain serviceable before it requires rehabilitation
such as an overlay. The analysis period is the amount of time
over which the pavement life is to be considered, including
any rehabilitation work. For high volume roads (collectors
and above), an analysis period of at least thirty years is
frequently considered. For low volume roads (locals and below)
and all other pavements, a twenty-year life is generally acceptable.
As rehabilitation of flexible brick pavements cannot be achieved
by strengthening measures without lifting the bricks, this
Guide considers the analysis period as the design life of
the pavement.

AASHTO Design Concepts
[top]
The AASHTO Design Guide is based upon empirical
test results from full-scale road tests conducted in the 1960’s.
As a result of the measured behavior of the test sections,
the researchers developed a performance equation upon which
design of new pavement sections can be achieved. The equation
relates the design life, in terms of 18 kip ESALs, to a number
of different input parameters. These include the reliability
of the pavement, the acceptable level of loss in serviceability,
the variability of the traffic predictions and performance,
the structural number and the average subgrade resilient modulus.
The reliability of the designed pavement section
is an important feature in the AASHTO design process. The
reliability of the pavement is the probability that it will
perform satisfactorily over its design life for the traffic
and environmental conditions experienced. The reliability
level adopted in this Guide is taken as an 85 percent likelihood
that the pavement will reach its design life (analysis period)
for pavements with high traffic volumes (collectors and above);
and a 75 percent likelihood that the pavement will reach its
intended design life for pavements with low traffic volumes
(locals and below). Non-highway pavements are also considered
to have a reliability of 75 percent. This means that 85 percent
or 75 percent of the pavements for each respective use would
achieve or exceed the design life.
The AASHTO design method uses a subjective measure
of the loss of serviceability and failure of the pavement.
It was developed as an interpretation of the quality of the
ride experienced by the average road user. A scale from 0
to 5 represents the quality of the ride and is known as the
Present Serviceability Index (PSI). A PSI of 0 represents
an impassable road while a PSI of 5 represents a perfect road.
The change between the initial and final (terminal) PSI, known
as the Serviceability Loss, used in this Guide is taken as
1.7 for high traffic volumes and 2.2 for low traffic volumes.
This is based upon an initial value of 4.2 and terminal values
of 2.5 and 2.0 respectively. This compares favorably with
those used for typical flexible pavements. An exception is
in pedestrian areas where the potential for trip hazards is
an important consideration. Therefore, a serviceability loss
of 1.7 is recommended in these locations. Other AASHTO reliability
parameters are presented in Table 6.
The variability of the traffic prediction and
pavement performance is taken as 0.35. This is comparable
with the figures used for flexible pavements using asphaltic
concrete as a surface course.
The structural number is the only parameter directly related
to the pavement section. It is derived from the layer coefficient
of each layer, the thickness of each layer, and the drainage
coefficient for each layer. This Guide is produced under the
assumption that adequate drainage will be provided to the
pavement materials such that the latter coefficient can be
taken as 1.0. Typical layer coefficients are presented in
Table 7, with the default values used in subsequent design
tables in this Guide.
The values presented in Table 7 can be used to
adjust the layer thicknesses derived from the design tables.
The ratio of the layer coefficients can be used to determine
the equivalent thickness of an alternative material. For example,
to include a 6-in. (150 mm) thick lime stabilized subbase
it is possible to reduce the aggregate base by 0.11/0.14 times
the 6-in. (150 mm) thickness, i.e. by 4.5 in. (114 mm). Similarly,
to replace 8.5 in. (216 mm) of graded crushed aggregate (CBR
100) with graded aggregate (CBR 60) multiply 8.5 by 0.14/0.12,
i.e. replace with 10 in. (254 mm) of graded aggregate. However,
it is recommended that the top of the aggregate base directly
under the paver setting bed always be constructed with graded,
crushed material that is 4 in. (100 mm) thick when the ESALs
are below 500,000 or 6 in. (150 mm) thick when the ESALs are
at 500,000 and above respectively.
AASHTO
Design Solutions [top]
Tables 8 through 11 of this Guide have been prepared
to provide design solutions to each pavement class and subgrade
category. The wearing surface is always a 2-5/8 in. (67 mm)
paver on a 1 in. (25 mm) setting bed. The bituminous setting
bed is usually specified at 3/4 in. in thickness, and an adjustment
to the developed thicknesses is required as discussed in the
bituminous setting bed section. The base is as indicated in
the tables.
Table 8 presents the thickness of graded aggregate
subbase course required for each application. The resultant
pavement section will be comprised of 2-5/8 in. (67 mm) thick
flexible brick surface on 1 in. (25 mm) of bedding sand, over
4 in. (100 mm) of crushed, graded aggregate base on top of
the thickness of graded aggregate subbase determined from
the table. Note that the thickness of crushed, graded aggregate
base is increased from 4 in. to 6 in. (100 to 150 mm) for
traffic levels over 500,000 ESALs. An unbound base course
is not considered appropriate for traffic levels above 2,000,000
ESALs.

Similarly, Table 9 provides the required thickness
of graded aggregate subbase when a cement treated base is
used under the bedding sand. Note that in this case the thickness
of cement treated base is increased from 4 in. to 6 in. (100
to 150 mm) for traffic levels over 2,000,000 ESALs. Table
10 can be used when an asphalt treated base is provided.
Table 11 provides typical portland cement concrete
slab thicknesses, with a 4 in. (100 mm) aggregate subbase
below and a wearing surface of flexible brick paving. This
table is for guidance if the bricks are to be used over such
a substrate. Little structural benefit is provided by the
bricks in this pavement section, and care needs to be exercised
in ensuring that detailing allows for thermal and moisture
induced movement in the concrete, and for egress of moisture
penetrating the brick surface.
CALTRANS
Design Concepts [top]
The Caltrans design method is also based upon
a wide range of information including: theory, test track
studies, experimental pavement sections, observations of pavement
performance, and research on materials. Pavements are generally
designed for a twenty year life, but it is accepted that asphalt
concrete surfaced pavements will require maintenance at ten
to fifteen years if they are to achieve this life. This is
generally a surface material issue, and this Guide assumes
that the brick pavers will provide a twenty year life.
The Caltrans design method considers the various
pavement materials in terms of a gravel factor (Gf). Tables
are included in the Caltrans design manual setting out the
gravel factors for various materials dependent on the materials
properties and the TI. The gravel factor is a representation
of the relative ability of the materials to resist the effects
of traffic loading, when compared to an equivalent thickness
of gravel.

The design of the pavement section is based upon
a relationship between the R-Value (R), and the Traffic Index
(TI) to develop the Gravel Equivalent (GE) for the pavement.
The relationship is represented by Equation 4:
GE (mm) = 0.975 X (TI) X (100-R)
(Eq. 4)
The procedure is carried out from the top of
the pavement to the bottom. Treated base layers generally
have an R-value greater that 100 and so the equation is typically
applied to the highest layer in the pavement section with
an R-value less than 100. The thickness of the overlying layers
is determined. The process is then used for the underlying
layer, and so on down to the subgrade. The thickness of each
layer is calculated by dividing the GE by the appropriate
Gf. The thickness of each layer is generally rounded to the
next 0.05 ft (15 mm) increment.

To allow for deviations from the specified thickness
as a result of construction procedures the Caltrans method
uses a safety factor procedure. This involves adding 0.2 ft
(60 mm) to the GE of the asphalt concrete surface material
and subtracting 0.2 ft (60 mm) from the GE of the subbase,
or if no subbase is used, from the thickness of the base.
The thickness of the brick pavers cannot be changed, and so
this practice needs to be undertaken between the base and
the subbase, if used.

Design solutions using the Caltrans procedure
are not presented in this Guide, however, a Gf of 2.0 is proposed
for the brick paver and sand setting bed, and 1.8 is proposed
for the brick pavers on a bituminous setting bed, based upon
the above noted typical relationship with equivalency to asphalt
concrete. This value can be used when the Caltrans manual
is appropriate for the design, rather than the AASHTO methodology.

Design of Bituminous Setting Bed Systems
[top]
Bituminous setting bed systems as shown in Figure
6b can be used in most of the same applications as sand setting
bed systems. Higher speed apllications are less desirable
as the interlock between pavers is reduced. Although it has
reduced structural benefits, the system can provide better
moisture protection to the underlying layers. In addition,
the bonding action of the system enables the use of pavers
with a lower standard of dimensional tolerances where wider
joints would lead to reduced “lock-up” in a sand
set system. Joint widths of up to 1/4 inch (6mm) can be tolerated,
especially in low traffic applications. As there is no vibration
used to compact the pavers, chipping is less of a problem,
particularly with pavers that do not have chamfers or lugs.
This system may also have advantages where edge restraints
are less reliable, or where movement may be encountered. This
typically occurs where pavers are placed against steel rails
for light rail applications.
The bituminous setting bed system can be used
as an alternative to a sand setting bed system. The 1 in.
(25 mm) thick sand setting bed is replaced by a 3/4 in. (19
mm) thick asphalt coated sand mixture that is “bonded”
to the underlying pavement layer using a tack coat. The brick
pavers are bonded onto this layer with a rubberized asphalt
adhesive. The joints are filled with stabilized sand, but
no vibration is used. Consequently, “lock-up”
is not as well established and the load spreading is reduced.
The base thicknesses presented in this Guide can be used for
this system; however, the thickness of the underlying layers
needs to be increased. This can be achieved by adding an additional
1 in. (25 mm) to the thickness of the cement treated base
layer, 3/4 in. (19 mm) to the thickness of the asphalt treated
base layer, or 1-1/2 in. (38 mm) to the thickness of the graded,
crushed aggregate base. No revision is necessary for the portland
cement concrete sub-slab option.
Mortared Brick Paving [top]
The structural design of mortared brick paving
follows the design of rigid pavements. The brick pavers and
the mortar setting bed are not taken into account in the thickness
design. The design of mortared brick paving is not the aim
of this Guide. Refer to the AASHTO Design Guide or BIA Technical
Notes 14 Series.
Detailing
Surface Profile [top]
Satisfactory slopes for flexible paving must
be provided to avoid ponding water. A minimum slope of 2 percent,
(1/4 in. per foot or 1 mm per 50 mm), is suggested for all
exterior brick paving. Crowns on roads usually provide adequate
slope. A maximum slope of 10 percent is recommended for flexible
brick streets and roads, since larger slopes will cause washout
of the jointing sand and braking vehicles will increase the
creep of the pavement. Surface grades of up to 15 percent,
or even 20 percent, can be used on pavement areas subject
to slow moving traffic or pedestrians. However, joint sand
stabilization, as well as a high level of installation quality,
is desirable to reduce creep that occurs.
Drainage [top]
Drainage is one of the most important design
requirements, since improper drainage may cause failure of
the pavement, erosion of the base or subbase, possible deterioration
of the pavers, or slippery pavements. Drainage needs to be
considered at three levels in the pavement. These are at the
surface, to the setting materials and to the pavement structure
and subgrade. Surface drainage is undertaken in accordance
with standard design concepts for pavement areas. The pavement
surface should be finished 1/8 to 1/4 in. (3 to 6 mm) above
drainage gratings to allow for potential secondary compaction
of the setting bed under trafficking. Surface profiles are
covered in the previous paragraph. The bond pattern may affect
the flow rate of water over the surface of the paving, as
water tends to flow along the joint lines. Surface runoff
will increase with time as the joints become filled with debris,
however, some water will penetrate the brick surface layer.
Water that penetrates the wearing surface should
be drained away from the setting bed and base when the underlying
layers are not free-draining. This is particularly the case
when the setting bed is placed over a portland cement concrete
slab or a cement or asphalt treated base. Weep holes placed
vertically through the portland cement concrete slab may be
necessary depending on the environmental conditions. Drainage
is less of a concern with bituminous setting beds as some
water will percolate through them. It may be necessary to
provide a sub-surface drainage system. Sub-surface drainage
weeps should be provided at low points and at the edge restraints
to drain water to the pavement edge or storm drains. A perforated
pipe wrapped with an appropriate geotextile material may be
used. The geotextile is necessary to keep small particles
from washing out of the setting bed into sub-surface drains.
A drainage layer of open graded aggregate may also be used,
but requires proper planning, designing and specifications.
Design and detailing of such systems are not included in this
Guide, and the reader is directed to the references for several
manuals on this subject.
Bond Patterns [top]
Many different bond patterns exist, providing
different aesthetic effects, a few of which are shown in Figure
8. Herringbone provides the best resistance to the horizontal
forces from accelerating, braking and turning of wheels, and
should be used in areas subjected to heavy vehicular traffic.
This is required for sand setting beds and recommended for
bituminous setting beds. The pattern can be oriented at 45
degrees or 90 degrees to the direction of traffic. It is not
necessary to turn the pattern at corners and bends, as the
horizontal interlock is good in all directions.
Many of the pavements laid in the 19th and 20th
Century were laid in running bond, either directly across
the streets, or occasionally at up to 45 degrees across them.
Running bond patterns have continuous joints in one direction.
They do not transfer loads well along the continuous joints,
and so careful consideration is necessary with their use.
They require smaller joints between pavers in order to minimize
creep. Running bond pattern is not recommended for high volume
roads and streets. For low traffic volume paved areas the
traffic should run perpendicular to the direction of the continuous
joints.

Other bond patterns, such as basketweave and
stack bond, can be used in pedestrian areas. This also applies
to derivations of these patterns, such as Spanish bond. In
all of these arrangements, the patterns include continuous
joints in two perpendicular directions. For most basket weave
patterns laid in a flexible pavement the bonding ratio of
the paver is 2:1 or 3:1 (length: width) for proper alignment
of the pattern. Herringbone bond, running bond and stack bond
do not have to follow this rule, although joints will not
align with a herringbone bond using an irregular module, which
may affect installation quality. Basketweave and stack bond
patterns tend to show irregularities of the pavers and misalignment
of the bond pattern more than other bond patterns. Great care
needs to be exercised with such patterns if there is any likelihood
of in-place wheel turning.
Some pedestrian plazas and other facilities have
been installed using the brick pavers in modules that coincide
with the building grids, tree pits, or other features. Other
designs have been created in herringbone bond or bands using
different color pavers. When setting out a pattern using fixed
dimension modules or different colors, it is important to
remember that the individual bricks are not exact sizes. In
a modular pattern a consistent 1/16 in. (2 mm) under or over
sizing of the bricks, allowable in standard manufacturing
tolerances, will soon lead to a shortfall or overrun of several
inches in a grid module. This should only be overcome by cutting
the bricks to fit, as spacing the pavers with wider joints
can affect the structural integrity of the pavement. When
mixing different colors of pavers in a pattern area, it is
necessary to have an understanding of the potential for different
sizes so that the desired appearance is achieved.
Edge Restraints [top]
Edge restraints are necessary along the perimeter
of the pavement to prevent lateral movement of the pavers
and loss of the setting bed. The edge restraints should be
able to resist anticipated loads with minimal movement in
order to maintain interlock. Edge restraints can be placed
before laying the setting bed, and those incorporating concrete
should be cured before compaction of the brick pavement begins.
All edge restraints should be placed to a depth of at least
the bottom of the setting bed. Edge restraints are required
for both sand set and bituminous setting methods, although
the former requires more robust construction. It is important
that the inside face of the edge restraint is vertical so
that the pavers can be laid against it without a tapered joint
that will reduce the integrity.
Concrete Dividers and Inlays [top]
In many pavement areas, the brick pavers are
laid between concrete elements that divide the pavement into
sections. These are typically 8 to 16 in. (200 to 400 mm)
wide. The perception is frequently that this will provide
the opportunity to change the pattern orientation or that
by incorporating such fixed features it will be possible to
prevent creep of the brick pavers. In actuality, it introduces
a discontinuity into the pavement that creates a weakness
within the traffic area. Placement of small cut pieces, opening
of the joints, and settlement of the pavers often occurs at
these locations. Therefore concrete dividers are not recommended.
Changes in the pattern orientation can be formed by incorporating
a header or sailor course of bricks if a band type feature
is required, by a single sawcut joint line, or by a carefully
introduced series of staggered sawcut joints to maintain continuity.
Inlays are also frequently used where a panel
of brick pavers is incorporated as an entrance feature. Such
inlays are usually surrounded by concrete dividers, or portland
cement concrete pavement. When detailing such an inlay it
is important that the sides of the dividers are vertical so
that interlock can be generated between the bricks and the
concrete. The brick pavers should be finished approximately
1/8 in. (3 mm) high against the concrete so that there is
accommodation for secondary settlement of the setting bed
under traffic. It is also advisable to keep the cut pieces
of brick against the edge divider as large as possible, with
no pieces less than a quarter of a paver. Thin slivers are
particularly vulnerable to damage at these positions. Some
benefit can be gained by incorporating a header, sailor, or
string course adjacent to the concrete edge.
Traffic Buttons, Reflectors and Paint
Markings [top]
Traffic buttons are frequently used as lane markings
in streets and roads where snow clearance is not an issue.
These buttons and reflectors are generally secured on the
pavement surface with an epoxy adhesive. Setting onto individual
brick pavers can be detrimental to the pavement. The impact
from vehicle tires can loosen and even dislodge the bricks.
It is recommended that alternative means of lane markings
are adopted for brick pavers, or that larger, low-profile
buttons are used that fix to more than one paver. One effective
solution has been to inlay concrete pavers that have a specialized
top surface finish. As concrete pavers are typically 3-1/8
(80 mm) thick, they protrude above the pavement surface sufficiently
to create tire feedback to indicate their presence.
There are several different types of traffic
marking methods for the pavement surface. These include adhesive
strips, paints, and thermo-plastics. When in service, the
individual brick pavers continue to move independently of
each other to a slight degree. As such, the joints open and
close a small amount when a wheel passes over them. This movement
is often sufficient to cause cracking of the adhesive strip
and thermo-plastic markings. Although thinner paint markings
frequently have a shorter service life on other pavement materials,
they may be more cost effective on brick paved surfaces. Where
the visibility of traffic markings is not a legislated requirement,
inlaying contrasting colored pavers can provide the most durable
option.
Movement Joints [top]
Pavement materials expand and contract as a result
of temperature and moisture changes. Flexible pavement materials,
such as aggregate, asphalt concrete and cement treated base
materials, distribute this movement over the entire pavement
areas such that localized strains are very small. As a result
the pavers are unaffected by the underlying movement. Brick
pavers behave similarly, with any movement taken up in the
joints between pavers without putting stress on the brick
or edging. Expansion joints are therefore not typically required
in such flexible brick pavements. However, when a portland
cement concrete slab, used under the flexible brick paving
wearing surface, expands and contracts, the movement is concentrated
at the joints between the slabs. This movement will be reflected
into the overlying pavers, which can be detrimental to the
pavement. When the concrete contracts, it causes the overlying
joints to open. This results in a loss of interlock, settling
of the pavers and a loss of integrity. When the concrete expands
it causes the joints to close. This can impose large horizontal
pressure into the brick paver layer, possibly causing paver
movement that may result in chipping and spalling of the pavers,
and in extreme conditions heaving of the surface. It is therefore
necessary to continue expansion joints through the brick and
setting bed layer by incorporating edge restraints on either
side of the joint. This should be applied to both sand set
and bituminous set pavers.
Portland cement concrete slabs are also provided
with contraction joints to control cracking during curing.
Movement at these locations is less than at expansion joints,
and it is not normally necessary to reflect the joints into
the surfacing if the underlying contraction joints are at
less than 10 ft (3 m) centers. In order to distribute the
movement over a wider area it is beneficial to cover the control
joints with a strip of geotextiles under the sand bedding
course. This is not done under bituminous setting materials.
Design Examples
Examples are available in the Adobe® Acobat
version of this file. To
download the file click here.
Part II: Materials
Introduction [top]
The performance of any pavement is only as good
as the base, subbase and soil on which it is laid. Quality
materials for every layer in the pavement system are vitally
important to good performance. Materials should conform to
state or local department of transportation (DOT) specifications,
ASTM standards, or other applicable industry standards. Project
specifications typically require submission of qualifying
tests set by the standards.
Base and
Subbase Materials [top]
Some pavement systems contain only a base, while
others contain a base and a subbase. See Figure 1 for location
of layers. The quality or type of base and subbase materials
is usually dictated by the design requirements. The design
tables are based on various CBR values for the aggregate layers,
and compressive strength or Marshall stability for the cement
and asphalt treated layers.
Base materials may consist of unbound granular
materials, such as crushed aggregate; cement-treated or asphalt-treated
aggregates; or concrete and asphalt bases. Subbases are usually
composed of aggregate materials. Aggregate base and subbase
materials, including cement- and lime-stabilized materials,
are commonly specified in local state and municipal standards
for highway construction. All materials should conform to
state or local DOT specifications. Materials conforming to
ASTM or other industry standards can be used as alternates.
The choice and quality of base and subbase materials influences
the performance of the pavement. Typically, each layer material
can resist progressively higher stresses from the subgrade
upward to the wearing course.
Aggregates [top]
The National Stone Association has provided gradation
limits for base and subbase aggregate materials, see Table
12. This table is similar to requirements found in ASTM D
2940 Specification for Graded Aggregate Material for Bases
or Subbases for Highways or Airports.
Crushed, quarry processed aggregate is preferred
because of its ease of construction. The maximum size of aggregate
to be used in construction may depend on the size of the project
and the size of equipment being used. Proper gradation of
materials is required to achieve adequate compaction. Layers
consisting of single-size aggregate will not consolidate during
compaction and should not be used.
For flexible brick pavements subjected to pedestrian
and light vehicular traffic, aggregate graded to “3/4
minus”, similar to the gradations in Table 12, is usually
sufficient as a base material because it is easy to work with
and is readily available. Smaller graded aggregates or rounded
aggregates may not be sufficient to achieve interlock within
the aggregate layer and will not transfer loads properly.
Open graded (gap graded) aggregates can be used to promote
water drainage in areas subjected to frost heave to minimize
damage. Geotextiles may be needed to prevent intrusion of
smaller material into the open graded aggregates.
Asphalt Bases
New or existing asphalt bases can be used for
flexible brick pavements. Specification of asphalt concrete
should follow industry standards or local DOT requirements.
The adequacy of existing asphalt and the materials beneath
should be verified.
Concrete Bases [top]
New and existing concrete bases can be used for
flexible brick pavements. New concrete slabs should be specified,
with reinforcement as needed, and constructed according to
industry practice. Concrete bases should be properly cured
before installing the flexible brick paving. High early strength
cement may be used to reduce the time before the wearing surface
is placed. Existing concrete slabs should be checked for appropriate
strength and repaired or reinforced as necessary. A geotextile
can be used where there is a possibility of loss of sand through
cracks or holes in the existing slab. The adequacy of the
materials beneath the existing concrete slab should be verified.
Soil and
Base Stabilization [top]
Subgrade soils or granular material unsuitable
for use alone may be treated to produce a stronger layer.
The subgrade soil may be stabilized by adding portland cement
or lime, depending on the quality of the soil. Subbase and
base materials may be improved by adding portland cement,
lime, asphalt or pozzolanic materials. Modifying unsuitable
materials is considered when economically feasible or where
suitable untreated materials are in short supply, although
caution should be used in specifying treated soils. Their
use should be based on local availability and experience.
Subgrade soils or granular material unsuitable
for use alone may be treated to produce a stronger layer.
The subgrade soil may be stabilized by adding portland cement
or lime, depending on the quality of the soil. Subbase and
base materials may be improved by adding portland cement,
lime, asphalt or pozzolanic materials. Modifying unsuitable
materials is considered when economically feasible or where
suitable untreated materials are in short supply, although
caution should be used in specifying treated soils. Their
use should be based on local availability and experience.
Aggregate subbase materials, as well as cement-
and lime- stabilized materials, are commonly specified in
local state and municipal standards for highway construction.

Setting Beds
Sand Setting Bed [top]
Sand used as the setting bed should be a washed,
well-graded, sand with a maximum size of about 3/4 in. (4.8
mm). Sand conforming to ASTM C 33 Specification for Concrete
Aggregates is acceptable. Table 13 shows the gradation limitations
taken from ASTM C 33. In addition, the amount of material
passing the 75 µm (No. 200) sieve should be limited
to no more than 3 percent. The sand particles should be sub-angular.
For pavements subjected to heavy channelized traffic, experience
has shown that only naturally occurring, washed silica sand
with no silt content should be used. The gradation for the
silica sand in channelized traffic should be as shown in Table
14 and no more than 0.3% passing the 75 µm (No. 200)
sieve.
An excess of fine particles can increase the
moisture sensitivity of the bedding sand. Bedding sands with
high fines content can lead to rutting and movement forms
of distress. It is not only important to ensure that the fine
content is satisfactory on the selected bedding sand, but
also that it will not break down under heavy traffic. A degradation
test can be undertaken on the bedding sand to compare different
bedding sand options. The test involves rotating sand samples
|